Overview

Chumisa

2016 EWB-USA Premier Project

The Chumisa Vehicular Bridge in the municipality of Joyabaj, Guatemala is a 42-ft clear span reinforced concrete girder bridge. This bridge crosses a river that regularly floods during the wet season of December-April and is not able to be crossed on foot or by vehicle. The river is near the border of a neighboring municipality, Cubulco, whose residents often want to travel to Joyabaj for the larger regional hospital and markets. This bridge will provide year-round reliable access to schools on either side of the river as well, and thereby ensures that rural communities will not be cut off from education, healthcare, and economic development during a large storm.

We would like to acknowledge the assistance of the EWB-Wisconsin Professional Partners on this project. They provided funds, design mentorship, travel mentorship and this project would not have been possible without them.

Project Manager: Riley Padron

Faculty Advisor: Douglas C. Stahl, Ph.D.

Responsible Engineer in Charge: Steve Berg, PE

Structural Design Mentor: Mark Maday, PE

Geotechnical Design Mentor: John Siwula, PE

Water Resources Design Mentor: Gary Raasch, PE, CFM

Special thanks to Mike Paddock and Kevin Hagen for additional design mentorship.

Implementation
Design
Trip 1

Pouring concrete for bridge footing.

Trip 1

Finished bridge footing.

Trip 1

Tying abutment wall rebar.

Trip 1

Erecting the abutment wall formwork panels.

Trip 1

Tying abutment wall panels together with walers.

Trip 1

Completed abutment wall formwork with ramps for pouring concrete.

Trip 1

Pouring the concrete for the abutment wall.

Trip 1

Finished abutment wall.

Trip 1

Formwork to support poured beam concrete.

Trip 1

Beam formwork frames in place.

Trip 1

EWB-MSOE student travelers.

Trip 2

Finishing beam formwork.

Trip 2

Carrying beam rebar cages into place.

Trip 2

Setting beam rebar cages to height.

Trip 2

Pouring concrete for the beams.

Trip 2

Finished beams.

Trip 2

Tying wingwall rebar.

Trip 2

EWB-WPP traveling mentors.

Trip 3

Tying the deck rebar.

Trip 3

Pouring the bridge deck.

Trip 3

Finished bridge deck.

Trip 3

Erecting wing wall formwork.

Trip 3

Finished wing wall formwork.

Trip 3

Pouring the wing walls.

Trip 3

Pouring the guardrail posts.

Trip 3

EWB-MSOE student travelers.

Finished Bridge

Bridge opened for traffic May 18, 2016.